Gas catalytic converter activated carbon filter installation
An activated carbon filter system with a gas catalyst sourced from Sweden, purifying 55,000 m³/h of air from solvent vapours. Elister OÜ carried out a 150 m rectangular duct air trunk line (1500 x 1000 mm), the installation of the filter system, and the automation cabling. The work was completed in accordance with the client's requirements and confirmed Elister OÜ's capability to take on the main contracting of larger projects.

Project challenge
As production volumes increased, so did the VOC volumes, for which an effective solution had to be found. For Elister OÜ, the challenge lay in the installation of an extensive air duct system and the comprehensive assembly of the entire system.
How we built the solution
A gas-catalyst activated carbon filter system procured from Sweden was installed, together with the necessary air ducting and automation. The work involved both the extensive installation of ducting and the routing of the automation cabling.
- Gas-catalyst activated carbon filter system
- Purification capacity of 55,000 m³/h of air from solvent vapours
- 150 m rectangular duct air trunk with dimensions of 1500 x 1000 mm
- Routing of automation cabling
Result
The work was completed in accordance with the client's requirements. The Elister OÜ team proved its capability to take on the main contractorship of larger projects.
Galerii
FAQ
Frequently asked questions
What is the cleaning capacity of the filter system?
What work did Elister OÜ carry out as part of this project?
How long was the installed air duct and what were its dimensions?
Why was such a filter system needed?
Projects
More similar projects
Factory Vacuum Compensation with Ventilation Unit
We installed a water-heated ventilation unit together with control automation and a water node at the factory of window manufacturer Viljandi Aken ja Uks to compensate for the air extracted by various equipment. The system ensures air exchange at a volume of 20 000 m³/h, filters the supply air with filtration grade M5, and heats the air to a level suitable for the indoor climate.
Ventilation of the press room in the production facility
For the press room of Tarmeko LPD's new production building, we prepared the ventilation design and working drawings, supplied the equipment, and carried out the installation. Forming with the presses generates fumes, which is why we built a solution where odours are extracted from above each machine and compensated with fresh, clean air. The result is an improved working environment and more comfortable working conditions.
Production facility heating solution with Metmann air curtains
The heating system at Nordwood's production facility was upgraded with three Metmann water-heated industrial air curtains. The units circulate air within the space at up to 25,000 m³/h, ensuring uniform heat and reducing the inflow of cold air through continuously open doors. The solution improved working conditions and also reduced energy consumption.