Manual finishing department: two paint booths and a drying tunnel
We established a dedicated manual finishing department for a long-term client to produce custom orders. We installed two 3-metre-wide finishing booths, six finishing pumps, a drying tunnel, and in-house manufactured GRINO drying trolleys. To ensure worker safety, we added barriers and fast-opening doors that separate the finishing area from the rest of production. The new department operates flawlessly and successfully fulfils all custom orders.

Project Challenge
The client needed to create a fully standalone manual finishing department capable of flexibly servicing custom orders. In addition to the equipment, it was essential to ensure employee safety and to clearly separate the finishing area from the rest of production. This required a well-thought-out spatial solution and a barrier system.
How We Built the Solution
As with every project, we first created 3D models and ensured that the solution met all of the client's requirements. After the technical components arrived, we began installation. To separate the finishing area, we installed barriers and fast-opening doors, allowing employees to focus on their work without disruptive factors.
Two finishing booths, each 3 meters wide Six finishing pumps for applying various substances A drying tunnel for fast and efficient drying In-house produced GRINO drying trolleys Barriers and fast-opening doors to separate the work area
Result
The new manual finishing department operates flawlessly and successfully fulfills all custom orders. The two wide booths and six pumps enable efficient and convenient work with various substances, while the drying tunnel and drying trolleys ensure fast drying. The client is satisfied with the solution, and the department supports the company's production of custom orders.
Galerii
FAQ
Frequently asked questions
How many paint booths were installed and how wide are they?
How many finishing pumps does the solution include?
How is fast drying ensured?
How is the finishing area separated from the rest of production?
How was the project planned before installation?
Projects
More similar projects
Manual finishing booths with drying tunnel and pump cabinets
For a returning customer, we manufactured wider manual finishing booths with a drying tunnel as well as specialized pump cabinets for paint pumps, into which safety leak trays were integrated. The solution was designed as a 3D model according to the customer's requirements, and in addition to the booths and pump cabinets, we organized all partition walls, doors, and finishing technology. The result was a fast and seamless implementation and a satisfied customer who received exactly the solution they wanted.
Renovation of a Door Manufacturer's Finishing Workshop – MAKOR Automatic Line and Manual Finishing Booth
An automatic finishing solution, MAKOR SPRAY & DRY – M, was designed and installed for a Central Estonian door manufacturer, together with a manual finishing booth built by Elister. The heart of the finishing process consisted of GRACO PerformAA automatic paint guns with Merkur-series pumps, and the ventilation was interfaced directly with the Makor system, which detects the operating equipment and adjusts the working modes. The entire system was designed, installed and commissioned into working order precisely during the factory's collective holiday, resulting in an energy-efficient and safe finishing environment.
Relocation of the fully automatic Cefla spraying line from Tallinn to Võru
We relocated the fully automatic Cefla finishing line from Askala's former premises to Wermo's new production hall in Võru. At the client's request, we rebuilt the line during the relocation and turned it 180 degrees in the opposite direction of operation, which required reconstructing the drying multi-level oven in mirror image. The work began in September, and the first start-up took place already in early November.