Elister installed an automation-controlled heat recovery system in the compressor oil cooling circuit for AQ Lasertool OÜ, directing the residual heat of the 55 kW compressor into the building's heating system and domestic hot water. The system recovers an average of 10 MWh per month, with an annual forecast of over 120 MWh, resulting in significant heating cost savings and reduced CO₂ emissions.

ClientAQ Lasertool OÜ
Compressor waste heat recovery for heating – forecast over 120 MWh per year
forecast over
120 MWh per

Project challenge

Production had a constant heating need and the compressor operated daily, but the waste heat of the 55 kW unit had previously gone unused. Payback calculations showed that directing the heat into the building's heating system provides a very fast return on investment, which is why it was decided to implement the solution.

How we built the solution

We installed an automation-controlled heat recovery system into the compressor's oil cooling circuit, which optimises heat exchange and prevents the compressor from overheating. Heat energy is directed both to the domestic water and the heating water, and all parameters are adjustable.

  • Automation-controlled heat recovery system
  • Oil and domestic water/heating water temperature regulation using four sensors
  • Built-in heat meter for accurate measurement of recovered energy
  • Directable both to domestic water and the building's heating system

Result

Based on the first results, the amount of recovered energy averages 10 MWh per month. During the winter months, an even greater result is expected, as the higher temperatures of the heating system enable more efficient heat transfer due to the small temperature difference. The projected annual amount of waste heat is over 120 MWh, which means significant savings in heating costs and a reduction in CO₂.

Galerii

FAQ

Frequently asked questions

How much energy does the system recover?
The system recovers on average 10 MWh per month, with an annual forecast of over 120 MWh — meaning significant heating cost savings and reduced CO₂.
Where is the waste heat directed?
The 55 kW compressor's waste heat is directed to both the building's heating system and domestic hot water; all parameters are adjustable.
How is recovered energy measured?
The system has a built-in heat meter for accurate measurement of recovered energy, and temperature is regulated with four sensors.
Is the result greater in winter?
Yes — even better results are expected in winter, as the heating system's higher temperatures allow more efficient heat transfer due to the small temperature difference.

Projects

More similar projects

SoojustagastusKiiu · 2023

Hot-dip galvanizing exhaust air heat recovery and vacuum compensation

At Galv-Est AS's hot-dip galvanizing plant, the 45,000 m³/h of air extracted above the zinc bath created a strong vacuum and significant loss of thermal energy. We installed a ventilation unit with a plate heat exchanger featuring corrosion-resistant elements, which recovers heat from the galvanizing process and compensates for the vacuum. The solution enables efficient use of heat even at temperatures down to -25°C without additional heating.

SoojustagastusPärnu · 2023

The paint line heat recovery system reuses the furnace's residual heat

For Scanfil's new Gema automatic paint booth, we implemented a two-stage heat recovery system together with a ventilation unit featuring cooling capability. The residual heat released from the oven, which previously went to waste, is now directed into the central heating system of the production facilities and also covers the energy requirements of the added system. According to the forecast, the investment will pay for itself in approximately five years.

SoojustagastusSaue · 2023

Powder Coating Line Heat Recovery System

Elister installed a heat recovery system alongside Sami AS's new powder coating line, which reuses the heat from the hot air exiting the powder oven for heating. The heat is directed to maintaining the temperature of the metal washing bath, to the central heating system, and to the ventilation of the paint and assembly workshop, requiring no additional energy source. The system's projected payback period is approximately **5 years**, likely even shorter due to rising energy costs.

Sarnane väljakutse?Räägime, kuidas saame aidata.
Request a quote →