Robotic welding ventilation at the Narva factory
Two robotic welding workstations were established at Fortaco Estonia's Narva plant, together with an efficient welding ventilation solution. Above each robotic welding area, welding hoods with louvers mounted to the trusses were installed, the operation of which is controlled by the robot's control automation according to the section in which the robot is currently welding. We carried out the first installation in the spring, and we received the second identical order just a few weeks after the first one was commissioned.

Project challenge
Every metalworking industry deals with the welding of materials and the resulting gaseous and solid residues, which without appropriate ventilation turn the production air an opaque blue and reduce its quality. Since the welding robot has two work areas where the welding process takes place, it was necessary to cover the entire relevant welding area as efficiently as possible.
How we built it
The robotic welding workstations were built by OMD OÜ, and our contribution was in the form of welding ventilation. To the trusses created next to the workstation, we mounted welding hoods with louvres, whose operation is controlled by the robot's control automation. The automation activates extraction precisely in the section where the robot is currently welding — this keeps the air clean without unnecessary energy consumption.
- Two robotic welding workstations
- Welding hoods with louvres mounted to the trusses
- The robot's control automation manages extraction of the relevant section
What we achieved
- Both robotic welding work areas covered
- Clean and high-quality production air
- Section-based extraction avoids unnecessary energy consumption
- A few weeks after the first commissioning, the client ordered an identical second installation
Galerii
FAQ
Frequently asked questions
How many welding workstations does this solution cover?
How is the ventilation's energy consumption kept low?
What equipment was used in the welding ventilation?
What result did the solution provide for the production air?
Was the client satisfied with the solution?
Projects
More similar projects
Welding hall ventilation solution with smart remote management
We built a push-pull general ventilation system for the welding hall with two separately controlled zones, ensuring a total air circulation of up to 60,000 m³/h (the requirement was ≥45,000 m³/h) and over 10,000 m³/h of fresh air. We installed two GRAM 364DH double cyclones with 45 kW fans and a C.I.C Jan Hrebec plate heat exchanger with water heating, which reduces heating demand. Compliance of air quality with health protection limit values was confirmed by measurements carried out together with the Health Board, and the entire system is controlled by a single control panel with real-time remote management.
Push-Pull welding ventilation for a metal production hall in Saue
At a metalworking company's production hall in Saue, we solved the blue welding fume problem using the Push-Pull method, as the use of welding arms was not possible due to the large components and continuous crane operation. We installed an FL series filter with GRAM welding cartridges, prepared a 3D piping installation drawing, and carried out the installation. The filtered air is directed into the hall from floor level, and the welding fumes are extracted from above the workstation, beneath the ceiling.
Factory Welding Workshop Push-Pull Ventilation
We upgraded the ventilation of the manual welding stations at Sami Tootmine's Valga factory in two areas, each with 10 workstations. We installed cyclone filters together with fans from the Danish manufacturer Gram Clean Air and designed a push-pull ventilation system with air calculations. We integrated automation that activates the filter system only when welding is actually taking place, ensuring energy savings and a clean working environment. In addition, we helped find a suitable welding filter for the robotic welding area.