A major overhaul was carried out on the heating elements of the post-priming infrared curing oven of Lappset Estonia's powder coating line, during which all infrared heating elements were replaced in cooperation with the manufacturer's representatives. The gas-catalytic infrared oven gels the powder coating before applying the topcoat, which enables two layers of paint to be applied consecutively and provides significant time savings, as products do not have to be passed through the curing oven twice.

ClientLappset Estonia OÜ
Gas-catalytic infrared oven renovation on the paint line

The project challenge

The post-priming gas-catalytic infrared curing oven of the Lappset Estonia powder coating line required a major overhaul. The oven's infrared heating elements had worn out and needed a complete renewal to ensure the reliability of the coating process.

How we built it

The work was carried out in cooperation with the factory's representatives. A gas-catalytic infrared oven is a good solution when two coats of paint need to be applied consecutively – a primer and a top coat. The infrared oven gels the powder paint before it is covered with the top coat, and after being coated with the top coat, the products undergo final full curing in the curing oven.

All infrared heating elements were replaced A major overhaul was carried out on the post-priming infrared curing oven

What we achieved

The renewed infrared oven allows two coats of paint to be applied consecutively Significant time savings, as products do not need to be passed through the curing oven twice Restored reliability of the coating process with new heating elements

FAQ

Frequently asked questions

What work did Elister perform on the Lappset Estonia paint line?
Elister renovated the gas-catalytic infrared curing oven used after priming, carrying out a major overhaul. All infrared heating elements were replaced during the work.
Why is a gas-catalytic infrared oven a good solution?
It is suitable when you want to apply two paint layers consecutively – primer and top coat. The infrared oven gels the powder paint before the top coat is applied.
What benefits did the oven renovation bring?
The renewed infrared oven allows two paint layers to be applied consecutively and provides significant time savings, as products do not need to pass through the curing oven twice. It also restored the reliability of the painting process with new heating elements.
Why did the oven require a major overhaul?
The oven's infrared heating elements were worn out and needed complete renewal. This was necessary to ensure the reliability of the painting process.
How was the work carried out?
The work was carried out in cooperation with the factory's representatives. The major overhaul was done on the infrared curing oven used after priming, and all infrared heating elements were replaced.

Projects

More similar projects

PulbervärvimineTartu · 2018

"Power&Free" conveyor fully automatic powder coating line

A modern powder coating line was designed and installed for Torm Metall OÜ, enabling the washing and coating of products with dimensions of 4500 x 1000 x 1800 mm. The solution included a chamber-based 7-stage washing line with separate cabins for ferrous metal and aluminium, a combi oven, and a fully automatic "Power&Free" conveyor system. In the combi oven, the residual temperature of the curing oven is utilised in the drying oven, which increases energy efficiency.

PulbervärvimineTallinn · 2023

Investment in a New Automated Powder Coating Line

We designed and installed a fully automatic powder coating line for Tammer, complete with an Aabo-Ideal gas- and electric-heated curing oven and a Gema paint booth operating 16 automatic guns. The monorail conveyor has a load capacity of 100 kg per metre. In addition, we built out the compressed air and ventilation lines. The entire installation was completed in May 2023, having started already before Midsummer.

PulbervärvimineSaue · 2022

Powder Coating Automatic Line with Power&Free Conveyor

For Sami AS, for whom we built a two-chamber liquid painting line in 2020, we established an automatic powder coating line as part of a production expansion. The solution includes a Power&Free conveyor and a tunnel-type washing automatic line that enables production analysis and future expansion. The equipment is sourced from reliable manufacturers Gema AG, Aabo-Ideal and Hjort-Conveyor.

Sarnane väljakutse?Räägime, kuidas saame aidata.
Request a quote →